Twin Eagle Sand Logistics expands Big Spring Terminal

Twin Eagle Sand Logistics expands Big Spring Terminal


Twin Eagle Sand Logistics, a subsidiary of Twin Eagle Resource Management, has further expanding the Permian Rail Park to meet the strong demand of the Midland Basin.

Phase I of the unit train capable rail park was completed in February of 2016 and comprised 33,000 feet of rail track for rail-to-truck frac sand trans-loading services. Phase II of the park includes 15,000 tons of flat storage, 7,800 feet of additional rail track and a 50% expansion of the transload road. Phase III will include the development of the rail park’s 150-acre Lot 2 parcel.

_rail-sept-1

The new development of Lot 2 will feature 30,000 tons of rail accessible vertical silo storage. Phase III of the park will break ground next month and will be completed by the first quarter of 2018.

For more information visit www.twineagle.com

5th June 2017